Skip to content
All articles
Data10 min

Prosumer (Buyer-Producer) in Republika Srpska: Steps, ERS Rules, and Return on Investment (2026)

How to become a prosumer in RS: power distribution consent, grid connection, net metering up to 10.8 kW, and an investment payback of around 5 years.

Author · Electrical engineerErmin Bošnjaković

How to become a prosumer (buyer-producer) in Republika Srpska: step-by-step (2026)

Updated: Nov 23, 2026 · E. Bošnjaković, Electrical Engineer

In brief: In Republika Srpska, a household becomes a buyer-producer, or prosumer, by first building and connecting the power plant, and then obtaining the status. The first step is submitting a request to amend the electro-energetic consent with the relevant power distribution company operating within ERS. This is followed by construction carried out by a licensed company, a connection contract, and a certificate for the production facility. Finally, a new supply contract is signed with the electricity supplier. A rooftop power plant up to 50 kW on a legal building does not require a building permit or location conditions. Up to 10.8 kW, excess energy is accounted for via net metering, kilowatt for kilowatt. Under the same conditions as in the Federation, a 10 kW plant pays for itself in about 5.1 years, and in about 4.1 years with a GEFF loan. This guide applies only to Republika Srpska; for the Federation of BiH, see our guide for prosumers in FBiH.

What is a buyer-producer (prosumer) and who can become one in Republika Srpska?

A buyer-producer, better known as a prosumer, is an electricity customer that generates energy for their own needs on their property. Excess electricity is fed into the grid and consumed later. This status was introduced in Republika Srpska by the Law on Renewable Energy Sources ("Sl. glasnik RS", No. 16/22). The details are governed by the Rulebook on Electricity Buyers-Producers ("Sl. glasnik RS", No. 80/23).

Any end customer can obtain this status: a household, company, entrepreneur, or farmer. The status is recorded in a registry maintained by the relevant ministry.

In Republika Srpska, the grid is maintained by the electricity distribution companies that are part of Elektroprivreda Republike Srpske (ERS): Elektrokrajina (Banja Luka), Elektro Doboj, Elektro-Bijeljina, Elektrodistribucija Pale, and Elektrohercegovina (Trebinje). You submit your requests to the one operating in the area where your house is located.

How to become a buyer-producer (prosumer): steps according to ERS rules

  1. Assessment of consumption and roof. Gather electricity bills for the last 12 months. The capacity of the solar power plant must correspond to annual consumption and must not exceed the building's approved connection capacity.

  2. Design project. The project defines the system capacity, panel layout, inverter, protections, and the metering point. The application to the electricity distribution company is submitted based on this design.

  3. Confirmation from the urban planning department. A rooftop plant of up to 50 kW that does not exceed the dimensions of the roof is considered an adaptation of an existing building. It does not require a building permit or location conditions. However, the ERS power distribution company still requires a certificate from the municipal urban planning department confirming that a building permit is not required for connection.

  4. Request to amend the electro-energetic consent. Submitted to the competent power distribution company prior to construction. The power distribution company determines the connection and metering conditions.

  5. Construction. The power plant must be built by a legal entity holding a license for the execution of electrical power facilities, issued by the ministry responsible for construction. Enora and our partners hold the required licenses to carry out works in Republika Srpska. For plants up to 50 kW, prior notification to the building inspector is not required.

  6. Connection and certification. A connection contract is concluded with the power distribution company, and a bidirectional meter is installed. For plants up to 50 kW, the power distribution company also issues a certificate for the production facility, which confers the status of buyer-producer, or prosumer.

  7. New supply contract. Once you acquire the status, the supplier (ERS) is obliged to sign a new supply contract with you with net metering or net billing.

Important: The urban planning department issues the confirmation that a building permit is not required only for legal and registered properties. If the house lacks a building permit or is not entered into the land registry, that process must be completed first. Without this confirmation, the power distribution company will not connect the power plant, even if it is already built.

Who does what in the process?

Step

Who does it

What you get

Design project

authorized designer

solar power plant design project

Building permit confirmation

municipal urban planning department

confirmation that a permit is not needed (legal and registered properties only)

Amendment of electro-energetic consent

ERS power distribution company

connection and metering conditions

Construction

licensed legal entity

power plant and certification documentation

Connection

ERS power distribution company

connection contract, bidirectional meter

Certificate (up to 50 kW)

ERS power distribution company

certificate for the production facility

Status registration

competent ministry

entry into the buyer-producer registry

Supply contract

ERS as the supplier

contract with net metering or net billing

Net metering or net billing: what applies in Republika Srpska?

For systems up to 10.8 kW, excess electricity is accounted for via net metering. Fed-in energy remains as a credit in kWh and offsets consumption in subsequent months, kilowatt for kilowatt.

From 10.8 to 50 kW, net billing applies. The excess is then treated as a monetary credit: fed-in kWh × retail price minus 5%. In the Federation of BiH, that deduction is 10%.

Rule

Republika Srpska

Net metering (credit in kWh)

up to 10.8 kW

Net billing (credit in KM)

from 10.8 to 50 kW, price reduced by 5%

Maximum power plant capacity

up to the building's approved connection capacity, aligned with annual consumption

Annual settlement

April 1st, for the previous 12 months

Excess after settlement

not paid out

Due to the annual settlement, you should not build a power plant larger than your needs. Any excess that remains unused on April 1st is forfeited, so system capacity should be calculated based on actual annual consumption.

How much does a prosumer power plant cost in RS and when does it pay off?

For a 10 kW power plant, the annual savings are about 2,162 KM, and the return on investment is around 5.1 years. Electricity in Republika Srpska has been 10% more expensive since February 1, 2026, due to an increase in network fees, making self-generation more valuable than before. We calculate based on the same conditions as in the Federation of BiH: 0.23 KM/kWh in the higher tariff (network fees and VAT included), production of 1,197 kWh per kW annually, 45% self-consumption, and 55% excess delivered to the grid.

Paket Plus 10 (10 kW, turnkey)

Price with VAT

Annual savings

Payback

Payback with GEFF (20%)

Metal roof

10,990 KM

approx. 2,162 KM

approx. 5.1 yrs

approx. 4.1 yrs

Tiled roof

11,990 KM

approx. 2,162 KM

approx. 5.5 yrs

approx. 4.4 yrs

Prices apply to locations up to 30 km from Sarajevo; for Banja Luka and other locations in RS, we confirm the exact price after an on-site inspection. The package price includes the design project and all paperwork required for connection. Above 10.8 kW, net billing applies, meaning each delivered kWh is worth 5% less, making the payback period slightly longer. A detailed calculation can be found in the article 10 kW Solar Power Plant: Price and Payback.

GEFF loan. All banks that finance solar power plants in the Federation of BiH through GEFF also do so in Republika Srpska, under the same terms and with a cashback incentive of up to 20% of the loan amount. Learn more in the article GEFF Loan for Solar Power Plants.

RS Eco Fund incentives. The Environmental Protection and Energy Efficiency Fund of Republika Srpska issues an annual public call for households. The 2026 call included solar power plants for self-consumption, offering financial support of up to 50% of the costs, capped at 5,000 KM per application. That call is now closed. A new call is expected next year.

The cost of the bidirectional meter and the adjustments to the metering point is borne by the prosumer, according to the technical requirements of the power distribution company.

How Enora handles the process for you

Enora d.o.o. designs and builds solar power plants for prosumers (buyers-producers) and takes care of all connection-related paperwork. Enora and our partners hold the required licenses to perform works in Republika Srpska:

  • we create the project design and prepare the application to amend the electro-energetic consent (the consent itself is issued by the power distribution company, not us);

  • we help obtain the confirmation from the urban planning department;

  • we install the solar power plant, perform testing, and provide certification documentation;

  • we manage the process all the way to connection, certification, and the signing of the new contract with ERS.

Warranties: 30 years for panels, 5 years for on-grid inverters, 10 years for hybrid inverters, and 5 years for installation workmanship. If you are deciding between a battery storage system and a system without one, read Hybrid or On-Grid Solar Power Plant 10 kW.

Contact us for an offer: send us your electricity bill via WhatsApp at +387 67 129 6666 or +387 67 149 6666. We will advise you on the recommended capacity and estimate your savings. Request an offer →

Frequently Asked Questions

Do I need a building permit for rooftop solar panels in RS? No, provided the plant is up to 50 kW, installed on the roof of a property that already has a permit, and does not exceed the dimensions of the roof. However, the ERS power distribution company requires a confirmation from the urban planning department for grid connection, which is only granted to legal and registered properties.

Do I have to notify the building inspector before starting works? For power plants up to 50 kW, prior notification to the building inspector is not required. The plant must be installed by a company holding a license for electrical power facilities.

Who issues the certificate for the power plant? For plants up to 50 kW, the certificate is issued by the relevant power distribution company. For larger systems, it is issued by the Regulatory Commission for Energy of RS (RERS).

What happens to excess electricity? Up to 10.8 kW, excess energy is credited in kWh and rolled over to offset consumption in subsequent months. Reconciliation takes place once a year on April 1st, and any surplus remaining at that time is not paid out.

How fast does a prosumer power plant pay off in RS? The Paket Plus 10 (10 kW) on a metal roof costs 10,990 KM with VAT and saves about 2,162 KM annually. The payback period is around 5.1 years, or about 4.1 years with a GEFF loan. Following the electricity price increase in 2026, the calculations are even more favorable.

Do these rules apply in the Federation of BiH? No. The Federation of BiH operates under different regulations, a distinct incentive scheme run by the Operator for REiEC (Operator za OIEiEK), and a 10% deduction on excess electricity accounting. The payback math and GEFF conditions are otherwise the same. See our guide for the Federation of BiH.

Sources

Have a specific question?

An engineer replies within 24 hours, with no obligation.

Request a quote
Get in touch